Ports of Auckland restarts its automation project

Ports of Auckland (POAL) has announced a new plan to reset and complete its automation project, after its pause due to an incident in June that revealed a potential safety risk.

As the safety risk has now been fixed, POAL is ready to restart with a revised project that will be implemented in four stages, with the first to start shortly.

Each stage has milestones based on safety, reliability, productivity, and operational readiness, that must be met before the project can progress to the next stage.

Particularly, the four stages are the following: Systems acceptance testing, Automation of part of Fergusson Terminal North Berth, Automation of all of Fergusson Terminal North Berth and Full automation of Fergusson Container Terminal (go-live).

Unlike other, larger ports, Auckland lacks space to build a new automated terminal off-line, and then turn it on when complete. "We are having to automate our terminal while still operating, making it a more complex project," said the port authority.

Despite the difficulties due to the pandemic, the project has successfully handled over 100 ships, but the speed and reliability of the system have space to further be improved.

Particularly, a safety review also found that the safety assurance framework for the project needed more work. The port stated that "we have done a great deal of work on safety assurance and this is ongoing. We are now able to bring in overseas experts from the vendor to help complete the project."

Although a review found it is realistic for the project to be completed by late March 2022, this timing could impact existing import volume demand and the peak export season and cause further supply chain disruption.

For this reason, the port in New Zealand announced it will not give a "go-live date" at the moment.

Source: Container News


Related News

Maersk introduces new Middle Corridor rail service
Maersk introduces new Middle Corridor rail service

A.P. Moller - Maersk has decided to launch a new service linking China and Europe via Kazakhstan, Azerbaijan, Georgia, and Romania in about 40 days.

Port of Los Angeles to handle 85,000 metric tons of Chilean fruit imports during winter season
Port of Los Angeles to handle 85,000 metric tons of Chilean fruit imports during winter season

This week, the Port of Los Angeles welcomed the initial vessel of Chilean fruit for the year, carrying over 5,300 pallets loaded with grapes and stone fruit.

The Alliance announces changes in its Transatlantic services
The Alliance announces changes in its Transatlantic services

The Alliance, comprising Hapag-Lloyd, Yang Ming, Ocean Network Express (ONE) and HMM, has announced several changes in its Atlantic Loop (AL) services.


main.add_cart_success